At Green Square Solutions, we deliver high-quality commercial refurbishments that are both timely and within budget. Recently, we had the opportunity to showcase our expertise with a full office refit for BP at the Triton Power, Salt End Cogeneration Power Plant. This challenging project required technical precision and strict safety procedures, which makes it a standout achievement for our team of commercial fit-out contractors.
The Scope of the Project
The project involved a complete strip-out of the second-floor office space, followed by the installation of various features essential to creating a modern, functional working environment. Our work included constructing new walls, completing tape and jointing, installing MF ceilings, and fitting a lay-in grid system. We also added glass partitions as well as high-quality tiling and IPS toilet cubicles.
Managing the site effectively was also a key aspect of this project. Given the setting of a power plant, strict safety measures were vital. We ensured that our team adhered to all safety procedures, which guaranteed the quality of work and the well-being of everyone on site.
Why BP Chose Green Square Solutions
Our previous work at the Triton Power Station involved smaller projects. Due to our track record of delivering challenging jobs safely, on time, and within budget, the client had confidence in our ability to handle their full office refurbishment.
Luke Smith from Triton Power Station said:
“After working with Tim and GSS in the summer of 2023 on a few smaller projects on the power plant, we quickly realised that he knew what he was talking about and was transparent with his costing and the time scales he was giving, and would always talk us through the process of the job. The 2nd floor full office refurbishment was coming out for tender, and between both of us, we could give them an office space that would blow their mind. All they asked was for it to be completed on time and on budget! Which he did! The staff were over the moon with what they got and said it is the best office block on the power plant (and they are hard to please!) I would have GSS on any of my projects and couldn’t recommend them enough.”
Project Timeline & Location
The job was located at Triton Power, Salt End Cogeneration Power Plant, and spanned a total of 12 weeks. The first four weeks were dedicated to the strip-out, whilst the full refurbishment process took eight weeks. Throughout this time, our team remained focused on delivering top-quality results, ensuring that every aspect of the project met Triton’s specific standards.
Expert Commercial Refurbishments with Green Square Solutions
Whether your business requires a comprehensive office refit or a more straightforward update, Green Square Solutions is your go-to for professional commercial refurbishments. Our experienced commercial fit-out contractors work closely with clients to deliver projects on time, on budget, and to the highest standard.
Contact us today to discuss how we can help transform your commercial space.